The soon-to-be-altered bike lane on E. Monument Street, in front of Fountain Baptist Church. Photo by Ethan McLeod.

Del. Robbyn Lewis is among the many Baltimoreans who wonโ€™t soon forget Gov. Larry Hoganโ€™s 2015 veto of the Red Line. Beyond abandoning a project to bridge geographically and racially segregated Baltimore, the governor also returned $900 million in federal fundsโ€”a move federal officials will remember when deciding what checks to write, Lewis said.

โ€œIt will be a long time before the Federal Transit Administration approves large transit infrastructure money for Maryland,โ€ Lewis, whoโ€™s among the three delegates representing District 46, grimly predicted. โ€œThe feds donโ€™t forget that.โ€

She worries Baltimore City is now running a similar risk with federal and state funds for cycling and multimodal infrastructure. Today, a Department of Transportation-hired contractor is set to repaint part of a protected bike lane along E. Monument Street, leaving the eastbound path intact while redirecting westbound users to the sidewalk. The modification will restore about a dozen street parking spaces in front of Fountain Baptist Church at 1215 E. Monument St.

DOT is making these changes at Mayor Bernard C. โ€œJackโ€ Youngโ€™s behest. Youngโ€™s spokesman Lester Davis said Tuesday they requested the alteration after hearing from โ€œsenior citizens and other members of this this community,โ€ who complained to the mayor they werenโ€™t considered when the lane was installed in 2018, and wanted their spots back.

โ€œFinding a way to return parking for our senior population became our top priority,โ€ Davis wrote in an emailed statement. โ€œOur second priority was to maintain the bike lane without removing it.โ€ The planned modification is a compromise, he said.

While Davis made no mention of the church, Lewis wrote a letter to Youngโ€”which she shared on Twitter Tuesday morningโ€”mentioning that the mayor relayed the concerns of Fountain Baptist Church members.

She also said Young suggested to her that cycling infrastructure is โ€œnot a concern of African American people,โ€ a notion she strongly protests, pointing to a number of black users sheโ€™s seen navigating Monument Street just this week. (Young countered he said no such thing; Lewis maintains he did.)

The delegate told Baltimore Fishbowl that she had appealed to the mayor in hopes of arranging a meeting between neighbors (including churchgoers), the mayorโ€™s office, cycling advocates and others, when โ€œit was still enough time to halt the orderโ€ modifying the lane.

โ€œMy offer wasnโ€™t accepted,โ€ she said. โ€œNaturally I felt disappointed, and in the meantime Iโ€™m also concerned about all the reverberating implications of the order, of the insistence on deconstructing the lane. Itโ€™s not just about the convenience or inconvenience of the directly impacted folksโ€ฆ It has impacts for Baltimore Cityโ€™s ability, broadly, to secure financing for transportation.โ€

Lewis has since met with the board of the church, whose members she said โ€œdeserve respect.โ€ However, they could not come to an agreement about the bike lane, she said.

Baltimore in 2017 adopted an addendum to its 2015 Bike Master Plan for a full separated bike lane network catering to car-less commuters across the city. Officials originally committed to spending at least $1 million annually to build out the lane network, and planned to seek matching state and federal funds from the Maryland Department of Transportationโ€™s Bikeways initiative and federal Transportation Alternatives Program, or TAP.

But the city has backed off of its commitment in its Capital Improvement Program funds for 2020-2025, advocates complained this winter. To the ire of multimodal transportation boosters, once-earmarked funds for the bike lane network were cut from the six-year budget plans, which would leave Baltimore ineligible for those matching funds for years at a time.

Jed Weeks, policy director for the cycling advocacy group Bikemore, said DOT has not shared any updates since about the plans for 2020-2025. A version of the Capital Improvement Program budget posted online indicates the city plans to spend no new money on cycling infrastructure.

The Maryland Department of Transportation, which administers TAP funds, said the city was awarded $542,150 total in Bikeways grants in fiscal 2017, 2018 and 2019, as well as $250,000 in promised TAP funding in fiscal 2018.

However, MDOT spokeswoman Erin Henson added, โ€œTo be clear, Baltimore City has not received any of these funds to date.โ€

Thatโ€™s because the state reimburses the city only after itโ€™s completed a project and has sent along an invoice requesting reimbursement. For the projects that netted the city those promised grants, the city โ€œhas not sent any invoices or requested reimbursement to date,โ€ Henson said.

With that caveat, available state announcements point to a recent acute drop in the last couple years for promised Bikeways funding, with $310,850 in grants awarded for projects in fiscal 2016 and $312,230 in fiscal 2017, compared to $70,000 in fiscal 2018 and $159,920 in fiscal 2019.

The former cycle track in front of the Enoch Pratt Free Libraryโ€™s Roland Park branch. Photo by Ethan McLeod.
The former cycle track in front of the Enoch Pratt Free Library’s Roland Park branch. Photo by Ethan McLeod.

Lewis pointed to other bike lane projects the city has walked back or delayed substantially, including the muchโ€“fussedโ€“over Roland Avenue cycle track. The North Baltimore lane was installed as part of a multi-million-dollar traffic-calming project several years ago, and was recently repainted to restore curbside parking for residents who complained. Bikemore said the Mayorโ€™s Bicycle Advisory Commission pegged the cost of that work at โ€œat least $140,000.โ€

Thereโ€™s also been slow progress on the Downtown Bike Network, originally slated to be finished in 2017. DOT has said it should be done this summer, though a number of sections are still incomplete, including a whole portion on Madison Street.

Weeks, of Bikemore, also highlights the delayed installation of a bike boulevard on Covington Street below Federal Hill, other boulevards planned for West Baltimore and additional examples.

Lewis worries the pattern of delays and alterationsโ€“even small ones like those being made to Monument Streetโ€“further put federal and state dollars in jeopardy.

โ€œIโ€™ve heard through channels that even Maryland DOT is looking sideways at any request from Baltimore for bike and pedestrian infrastructure,โ€ she said, โ€œand I donโ€™t blame them.โ€

And she laments that the city is spending more on removing, rather than adding to, its network of multimodal transportation infrastructure.

For the newest modifications, which basically include repainting part of about half a block of Monument Street, thereโ€™s been some confusion about how much they will cost. Lewis and cycling advocacy group Bikemore at first said officials pegged the cost at around $50,000, but DOT said today that itโ€™s actually โ€œless than $10,000.โ€ Bikemore executive director Liz Cornish said officials at a meeting of the Mayorโ€™s Bicycle Advisory Commission on Wednesday had since revised the cost estimate to around that amount.

Lewis acknowledged the modifications to Monument Street are of a โ€œmuch smaller scale than the Red Line obviously, but a federal dollar is a federal dollar.โ€

Cornish said this latest case on Monument Street points to a problematic trend of officials reacting to some neighborsโ€™โ€“not all, she points outโ€“complaints as soon as new infrastructure disrupts the status quo of Baltimoreโ€™s car-favoring streets.

โ€œCommunity input is valuable and important, and it should be taken into consideration, but it shouldnโ€™t be taken into consideration to the point where we are making streets less safe for the most vulnerable users,โ€ she said.

Lewis knows Baltimore isnโ€™t alone in reconsidering designs for bike lanes. Other cities like New York and Seattle have gone through the trial-and-error process of installing such infrastructure, only to modify or remove it after neighbors dispute its functionality. But Baltimore stands alone in its degree of resistance to introducing such infrastructure in the first place, she argued.

โ€œI donโ€™t think any other major city has shown this level of schizophrenia and irresponsibility when it comes to expanding safe and healthy mobility options for its own citizens,โ€ Lewis said. โ€œWeโ€™re famous for this at this point.โ€

Looking ahead, she said the city has โ€œgot to get this rightโ€ for Baltimoreans who lack access to cars. โ€œThis is bigger than bikes. This is a civil rights matter, this is a public health matter, and itโ€™s a fiscal matter for the city. And with all the challenges we have, itโ€™s something with very little effort we could actually get right.โ€

This story has been updated.

Ethan McLeod is a freelance reporter in Baltimore. He previously worked as an editor for the Baltimore Business Journal and Baltimore Fishbowl. His work has appeared in Bloomberg CityLab, Next City and...

One reply on “As DOT proceeds to alter another bike lane, delegate worries Baltimore is risking federal, state dollars”

  1. Ethan has identified a pattern to these removal and installation projects: Some residents complain once construction is complete. Why should residents learn about a well-intended project after construction? Why is Baltimore City’s design process so often lacking the local expertise, save for a few who seem to have the loudest or more influential voice? If all interested residents had the opportunity to attend a well-advertised series of public workshops during the design phase of these projects to hear pros and cons; to learn about various design concepts other towns are successfully using; and to discuss with designers and DoT staff face-to-face how they feel about aspects of design alternatives, there might be good chance for a single plan of consensus to be engineered and evaluated. This is how many places fix their urban design problems. Everyone talks in the beginning of the process. Everyone interested in having genuine authorship is welcome. The community comes away from the design process with a single, thought-out vision.

    Baltimore is different. Projects are built with minimal public input and some influence by vocal groups. Then outraged residents, be they seniors or parents with bike riding children or what have you, begin talking and soon yelling at the end of the process. Expensive do-overs and costly repeats of the exclusive process are frustrating and wasteful. Neighborhoods like Roland Park are pulling in different directions–for and against.